Informe Jurídico sobre la Resolución Nº 46 Laudo Arbitral - Arbitraje Ad Hoc seguido entre OBRASCÓN HUARTE LAIN S.A. y PROVÍAS NACIONAL

No Thumbnail Available

Date

2024-08-12

Journal Title

Journal ISSN

Volume Title

Publisher

Pontificia Universidad Católica del Perú

Abstract

En este informe jurídico se aborda un problema principal y tres problemas secundarios relacionados con la Resolución Nº 46 Laudo Arbitral - Arbitraje Ad Hoc seguido entre OBRASCÓN HUARTE LAIN S.A. y PROVÍAS. NACIONAL. El problema principal radica en la posible alteración de la ruta crítica de la obra. Se concluye que sí existe un impacto en la ruta crítica, contrario a lo que señala el Tribunal Arbitral. El primer problema secundario sobre el impacto de la ruta crítica por el comportamiento de un tercero ajeno al contrato de obra, se determina que sí es posible, toda vez que el retraso en la aprobación del Presupuesto Adicional Nº 10 incurrido por la Contraloría General de la República constituye una causa que no es atribuible al contratista. El segundo problema secundario se refiere a partir de qué momento se puede ejecutar un presupuesto adicional que excede el 15% del monto contractual. Se establece que la aprobación se da a partir de la emisión de la resolución por parte de la Contraloría General de la República, que dispone la aprobación del presupuesto adicional solicitado por la entidad contratante. El tercer problema secundario analiza si el contratista debe solicitar la ampliación de plazo por un adicional de obra sin la autorización de la Contraloría General de la República. Se concluye que no es posible, ya que, sin dicha aprobación, no se puede ejecutar el adicional ni obligar al contratista a solicitar la ampliación de plazo.
This legal report addresses one main problem and three secondary problems related to Resolution No. 46 Arbitration Award - Ad Hoc Arbitration followed between OBRASCÓN HUARTE LAIN S.A. and PROVIAS NACIONAL. The main problem lies in the possible alteration of the critical path of the project. It is concluded that there is an impact on the critical path, contrary to what the Arbitration Court indicates. The first secondary problem regarding the impact of the critical path due to the behavior of a third party unrelated to the work contract, is determined to be possible, since the delay in the approval of Additional Budget Nº 10 by the Comptroller General's Office the Republic constitutes a cause not attributable to the contractor. The second secondary problem refers to when an additional budget that exceeds 15% of the contractual amount is considered approved. It is established that the approval is given from the issuance of the resolution by the Comptroller General of the Republic, which provides for the approval of the additional budget requested by the contracting entity. The third secondary problem analyzes whether the contractor should request an extension of the deadline for additional work without the approval of the Comptroller General of the Republic. It is concluded that it is not possible, since, without said approval, the additional cannot be executed or the contractor be forced to request the extension of the deadline.

Description

Keywords

Contratos públicos--Perú, Arbitraje y laudo--Jurisprudencia--Perú, Derecho administrativo--Jurisprudencia--Perú