Lama Bustinza, José Andrés2016-01-19http://revistas.pucp.edu.pe/index.php/themis/article/view/19607/19703Any contractual operation has a risk, which can be assumed by one of the parties, as agreed. In this context, it is common for cases of delays due to concurrent causes imputable to both parties, which can generate a high difficulty when assigning the risk. In this article, the author explains, from a comparative perspective, the different possibilities of solution in front of cases related with the concurrent delay controversies. It analyzes the various doctrines developed both in the Civil Law tradition and in the Common Law.Toda operación contractual conlleva un riesgo, el cual puede ser asumido por una de las partes según lo convenido. En ese contexto, es habitual que se presenten casos de demora (por causas concurrentes imputable a ambas partes, lo cual puede generar una gran dificultad al momento de asignar el riesgo. En el presente artículo, el autor explica, desde una perspectiva comparada, las diferentes posibilidades de solución frente a las controverisas relacionadas con la mora concurrente. Se analiza las diversas doctrinas desarrolladas tanto en la tradición del Civil Law como del Common Law.application/pdfspainfo:eu-repo/semantics/openAccesshttp://creativecommons.org/licenses/by/4.0Demora concurrente: propuesta de solución A una responsabilidad compartidaConcurrent delay: proposed solution to a shared responsibilityinfo:eu-repo/semantics/articlehttps://purl.org/pe-repo/ocde/ford#5.05.01